4.23 Petition to be in
Hindi
4.23.1 A number
of objectors suggested that
Madhya Pradesh being a Hindi
speaking State, the Tariff
Petition should be in Hindi.
4.23.2 The
Commission directs the Board to
ensure submission of the Tariff
Petition in future, also in
Hindi.
5. ANALYSIS OF
BOARD’S PROPOSAL
5.1 Sale of Energy
In
the absence of Board’s audited
accounts and necessary data in
this regard, the passing of
tariff order is like shooting an
arrow in the dark. Item wise
sale of energy as given by the
Board in its petition and the
revised information was
scrutinised. The Commission
found that figures of sale of
energy against SLP connections
and agriculture consumers need
revision. Consumption estimate
for X-ray plants and electric
crematoria are not available but
these categories do not have any
significant bearing on the total
revenue as their consumption is
only nominal. However,
computation of revenue for
several categories such as
domestic, LT industry, HT, grid
tariff and slab tariff etc. can
only be approximate as
consumption against each tariff
sub-class within the same tariff
category is not available with
the Board.
5.1.1 SLP Connections
5.1.1.1 The data
for 1999-2000 supplied by the
Board shows a consumption of 23
kWh per month for SLP
connections. A single light
point consumer permitted to use
a 40 watt lamp, would normally
consume about 10 units per
month, if the lamp is used for
about 8 hrs per day.
5.1.1.2 A study
made by the Board for SLP
connections in Indore, Bhopal
and Ujjain regions showed the
consumption to be very high. It
varied from 25 to 460 units per
month, indicating gross misuse
of unmetered energy.
5.1.1.3 The
Government of Madhya Pradesh has
withdrawn the facility of free
electricity to SLP consumers
from January 2001 except for
SC/ST consumers below poverty
line who are entitled to free
electricity upto 20 units per
month for which the State
Government shall provide
subsidy. The total number of
such SC/ST SLP consumers is
estimated as about 2,50,000 and
remaining SLP consumers would be
treated as domestic consumers.
Accordingly the consumption of
electricity in case of above
SC/ST consumers (2,50,000) is
assessed at 20 units per month
per connection. The balance
17,05,435 SLP consumers as
estimated by the Board are
assessed at 60 units per month
per connection.
5.1.2 Agricultural
Consumption and Load Factor
5.1.2.1 The
number of agricultural consumers
in Madhya Pradesh State in the
year 2001-02 is estimated to be
12,28,772 of which only 1838 are
metered. Studies were carried
out for assessing consumption of
the agricultural consumers.
(i)
Study by the Board of 128
metered connections in Indore,
Ujjain, Bhopal, Rewa, Jabalpur
and Gwalior regions, showed
average monthly consumption
varying from 98.2 kWh/HP/month
to 165.53 kWh/HP/month.
(ii) Another study by
the Board based on cropwise
number of waterings / number of
running hours of pumpsets of
unmetered consumers in seven
regions, showed that there is
wide variation in consumption
ranging from 14.68 kWh / HP /
month for Sagar region to 220.36
kWh/HP/month for Indore region.
(iii) Study through
Consultant in Indore region
revealed that the average
consumption was only 130.77 kWh
/ HP / month.
The studies also took into
consideration the reports from
Uttar Pradesh and that of M/s
DESCON in this regard.
5.1.2.2 It was
found during the study that a
number of pumpsets were utilised
for providing drinking water.
Since there is no separate
tariff for pumpsets providing
drinking water, the assessed
hours for drinking water were
added by the Board to the hours
of irrigation arrived at on
crop-wise basis, but such use of
water, being commercial, cannot
be taken to be for agriculture
use.
DESCON report has assumed that
on each pumpset 2 nos. of 100
watt bulbs are used for lighting
purpose. As such lighting
consumption per connection has
been assessed on the basis of 25
units per month for 6 months.
This assessment based on adhoc
assumption is not acceptable to
the Commission.
Use of power from agriculture
connection for operation of
thresher, etc. has been assumed
for agriculture purpose.
The consumption per HP per month
from different studies works out
as follows:
Board’s
study
79.46 units / HP / month
(average for 7 regions)
Consultants study for Indore and
Ujjain regions
89.59 units / HP / month
The studies done by the Board
and Commission’s consultants
indicate that, there are large
variations in the usage of
irrigation pumps in different
regions of the State. The reason
for high usage in Indore,
Gwalior and Ujjain appears to be
selection of pumps near these
large cities where power
availability is better, as they
are being fed from town feeders
and also selection of
cultivators taking cash crops. A
statement showing the region
wise study done by Board
alongwith the verification done
by consultant for Indore and
Ujjain regions is given at
Annexure IV.
In
Indore, Board’s study shows an
average consumption of 220.36
units / HP / month, which is
very abnormal and unreasonable
and which means that a pump runs
for approximately 10 hrs per day
for all the 365 days a year,
which is practically not
possible. Consultants study of
Indore region shows an average
consumption of 130.77
units/HP/moth which the
Commission accepts. By only
modifying Board’s figure of
Indore region, the Load Factor
(LF) for the State for the year
2000-01 works out to 11.77% (say
12%). This LF has been taken for
2000-01. Based on this LF, the
agriculture consumption for the
year 2000-01 works out to
3640.33 MUs as against 4247.05
MUs indicated by the Board. This
will affect overall T&D loss for
2000-01.
5.1.2.3 The
Average Load Factor for 2001-02
The Board has assumed the LF for
agriculture consumers as 14% for
2000-01 whereas, as per sample
studies and counter checks by
the consultants, it hardly comes
to 12%, that too with liberal
approach and because of
non-availability of authentic
data of sample studies. The
Board, for the year 2001-02, has
assumed the LF of 18% whereas in
para 13-A(iii) of the petition,
the Board has indicated that for
a 4 HP pumpset, the consumption
during kharif crop would be 1000
units and for Rabi crop 3000
units. This means a LF of 15.3%.
Considering the LF of 12% for
2000-01 and Board’s own
submission as above, the
Commission has considered the LF
for 2001-02 as 15%, which means
that correctly assessed
agriculture consumption
projected for this year shall be
4659.00 MUs and not 5590.70 MUs
as indicated by the Board.
5.1.2.4 The
correct assessment of
agricultural consumption is
important on account of its very
significant weightage in the
total energy use in the State.
The flow of required amount of
energy to the agricultural
sector has also to be ensured in
view of the importance of this
sector to the State’s economy.
It is, therefore, necessary that
the power flowing to this sector
is correctly measured and plans
for future requirements are
based upon realistic measurement
of energy consumption in the
agricultural sector.
The Government of Madhya Pradesh
has declared the policy of
providing meters on all
un-metered connections including
agriculture. The Commission
directs that all unmetered
agriculture connections be
metered within 3 years from the
date of this order and that no
new connection shall be given to
any consumers without the meter.
Progress of metering be
submitted to the Commission on
quarterly basis.
It is also directed that for
the correct assessment of
existing agriculture
consumption, the following
action be taken by the Board.
(i)
Meters installed for sample
studies be changed to electronic
meters and be continued so as to
cover the consumption of the
whole year and also to give
realistic pattern of cropwise
consumption.
(ii)
All further meters installed for
sample studies should also be
electronic meters.
(iii)
The selection of agriculture
consumers for sample studies
shall be such that for every
region it represents different
types of consumers (large,
medium and small on open wells,
tube wells, perennial sources
like river / nallah, etc.),
different cropping patterns and
the number of crops, in
proportion to total number of
consumers of the aforesaid
nature.
The results of the above sample
studies would provide the basis
for deciding Load Factor (LF)
for 2002-03.