SHRI P.K. MEHROTRA
CHAIRMAN
SHRI SYED IQBAL HUSAIN
MEMBER (P)
Petition No. 264/2002
IN THE MATTER OF
Determination of Board’s HT & LT Tariff
application for various categories
of consumers for the year 2002-03
Madhya Pradesh State Electricity
Board, - Petitioner/Applicant
Shakti Bhawan, Vidyut Nagar, Jabalpur
PETITION UNDER CLAUSE-62 OF THE M.P. ELECTRICITY
REGULATORY COMMISSION (CONDUCT OF BUSINESS)
REGULATIONS, 1999 – FOR DETERMINATION OF TARIFF:
On behalf on MPSEB : Shri D.
Roybardhan (Retd. E.D.
of MPSEB) OIC of the Case Assisted by
Shri Bodh Kumar, Addl. S.E.,
MPSEB and other team of Officers.
The list of objectors from HT/LT category consumers
is separately annexed at Ann. I
Chapter 1
INTRODUCTION
1.2 In its Order dated 26th September, 2001, the
Commission directed (in clause 2.7 of the Order)
that MPSEB should file its Annual Revenue
Requirement for the succeeding financial year before
October 31,2001 and the proposal for fixation of
tariff upto 30th November, 2001. The petitioner,
MPSEB, has however, filed the combined petition for
ARR and tariff proposal after a significant delay.
It is directed that MPSEB must ensure rigid
observance of time schedule for Financial Year
2003-04 and subsequent years.
Procedural History
1.3 The Petitioner had brought an application
before the Commission on 20th May, 2002 and after
initial scrutiny of the Application in the
Commission’s office a technical session for
validation of data was arranged on 9th and 10th
August, 2002. During this validation session the
team of the following officers from MPSEB led by
Shri D. Roybardhan, OSD (Tariff) was present:
i) Shri D.S. Goindi, Chief Engineer
(Comm.)
ii) Shri R.P. Arora, Chief Engineer
(O&M)
iii) Shri R.K. Saxena, Additional Chief Engineer (Generation)
iv) Shri Chetan Jaiswal, Joint Director (Accounts)
v) Shri Bodh Kumar, Addl. SE and some other officers
1.4 On behalf of the Madhya Pradesh Electricity
Regulatory Commission the officers mentioned below
supported the Commission alongwith the Consultants,
namely M/s Power Finance Corporation Ltd.
i)
Shri H.D. Motiramani, Director (Engg.)
ii) Shri D.K. Dewan, Joint Director
iii) Shri S.K. Khiani, Dy. Director
(Generation)
iv) Shri D.K. Vyas, Dy.
Director (T&D)
v) Shri Ashok Sharma, Dy. Secretary
vi) Shri L.P. Sharma,
Legal Assistant.
1.5 During the technical session it was
discovered that there were serious deficiencies in
the data provided with the petition and therefore,
the petitioner was directed to report on 26th
August, 2002 with corrected and complete
information. The petitioner however failed to
appear on the appointed date and requested for
extension of time, which was allowed for one week.
However, after one week, the MPSEB once again
requested for extension of time and eventually
submitted the updated information only on 23rd
September 2002. After due scrutiny the Commission
accepted the Petition on 25th September 2002, and
ordered it to be registered as Petition No. 264 of
2002 (264/2002).
1.6 During the technical session and also during
subsequent meetings, the petitioner was asked by the
Commission to submit actual data for the year
2001-02, but there was persistent request for more
time by the officers of the Board.
1.7 It is regretted that till date some items of
the information required by the Commission have not
been made available and the Commission is left with
no option but to make assumptions and surmises. The
Commission is disappointed at the approach adopted
by the Petitioner towards the requirement of
furnishing full and complete information for
processing the tariff request.
1.8 In the first Tariff Order passed on 26th
September 2001, the Commission had directed that:
i) The Board shall ensure full
compliance with the regulatory and procedural
requirements of the Commission while submitting its
petition/proposal for determination of tariff in
future.
ii) The Board shall supply
information in the formats prescribed by the
Commission in the following manner:-
a. Information in forms prescribed in Part I of the
Appendix (‘A’ Series Forms) shall be filed annually
on or before 31st October of each year, irrespective
of whether or not tariff determination is sought
for.
b. Information in forms prescribed in Part II
of the Appendix (‘T’ Series Forms) shall be filed
alongwith the proposal for tariff determination on
or before 30th November each year.
1.9 An important development that has taken place
in the management of Madhya Pradesh State
Electricity Board must be mentioned here. The State
Government (Energy Department) issued an Order (vide
No.5555/RS/4//13/2001 dated 1st July, 2002) stating
that for the purpose of reorganization of M.P. State
Electricity Board, five companies named below have
been incorporated as wholly owned Government of
Madhya Pradesh Undertakings and as Limited Companies
under the Companies Act, 1956: a) Madhya Pradesh
Power Generation Company Ltd., (b) Madhya Pradesh
Power Transmission Company Ltd. (c) Madhya Pradesh
Madhya Kshetra Vidyut Vitran Company Ltd. (d) Madhya
Pradesh Poorv Kshetra Vidyut Vitran Company Ltd. and
(e) Madhya Pradesh Paschim Kshetra Vidyut Vitran
Company Ltd. The Power Generation Company and
Transmission Company were incorporated in November
2001 while the Distribution Companies were
incorporated in May 2002. The Order further
provides that the five companies will be acting as
the Agents of the MPSEB and business will be
conducted in the name of MPSEB only and consumer
bills shall continue to be raised in the name of
MPSEB. These companies have an Operation &
Management agreement with the MPSEB, which is
effective from July 1, 2002 subject to the five
companies obtaining the certificate of commencement
of business.
1.10 An application was moved before the
Madhya Pradesh Electricity Regulatory Commission on
28th June, 2002 by Madhya Pradesh State Electricity
Board seeking the approval and consent of the M.P.
Electricity Regulatory Commission under Section
21(2) of Madhya Pradesh Vidyut Sudhar Ahiniyam, 2000
for implementation of the Operation & Management
Agreement proposed between MPSEB and the
Transmission and the Distribution Companies set-up
by the State Government. It may be mentioned here
that the Madhya Kshetra Vidyut Vitran Company is to
take over the distribution and retail supply
activities in the Commissionaires of Bhopal,
Hoshangabad, Gwalior and Chambal; the Poorva Kshetra
Vidyut Vitran Company is to take over the
distribution and retail supply activities in the
Commissionaires of Jabalpur, Rewa and Sagar; and the
Paschim Kshetra Vidyut Vitran Company is to take
over the distribution and retail supply activities
of Commissionaires of Indore and Ujjain. While
dealing with the application of Madhya Pradesh State
Electricity Board filed on 28th June, 2002, the
Madhya Pradesh Electricity Regulatory Commission
passed an Order on 16th July, 2002, in which it has
been held that the Operation and Management
Arrangements shall be only an internal arrangement
between the Madhya Pradesh State Electricity Board
and the Companies concerned and the same will not,
in any manner, affect rights of any third party or
the consumers. The Commission further directed that
a valid licence is a requirement under section 14 of
Vidyut Sudhar Adhiniyam, 2000 and it provides for
certain duties and obligations to be fulfilled by
the Companies for entering into the business. The
Commission held that the Transmission and
Distribution Companies should make applications for
grant of licence as per procedure prescribed within
2 months of the date of the Order (16th July, 2002)
and that the State Government should finalise the
rules and transfer scheme as per provision of
Section 23 of Vidyut Sudhar Adhiniyam 2000 within
the next 6 months of the Order (16th July, 2002).
The Distribution Companies and the Transmission
Company have sought extension of time for moving an
application for obtaining the requisite licence and
have been permitted time till 30th November, 2002.
1.11 The Chief Minister’s Conference held
in March, 2001 had noted that large amount of dues
owed by the SEBs to the Central Public Sector
Undertakings (CPSUs) was a major impediment to
reforms and resolved to constitute an Expert Group
to recommend a one time settlement of outstanding
dues and recommend a programme for medium term
restructuring and reform of the SEBs. The Group was
constituted under the Chairmanship of Shri M.S.
Ahluwalia, Member, Planning Commission. Whether
SEBs should remain liable or should the dues be paid
by the State Governments was the major concern for
the consideration of the Expert Group. The Expert
Group’s report states that if SEBs are viewed as
purely commercial enterprises, then they should be
held responsible for settling their dues. However,
the Group also noted that “if this approach is
followed, the SEBs would have to meet the
rescheduled debt service obligation in future, in
addition to meeting their liabilities. The reality
is that they will find the task of meeting current
obligations very formidable, and it is, therefore,
difficult to believe that they will be able to cover
past dues also, unless power tariffs in future are
not only raised to economic levels as required to
ensure viability (after taking account of normative
improvements in efficiency which they are expected
to achieve) but also consciously set even higher
than these levels to provide a margin for
repayment. The Group noted that regulatory
authorities were unlikely to agree to build in a
cushion in future tariffs to allow for payment of
past dues.”
In view of these considerations, the Group felt that
it was appropriate for the State Governments to take
on the liability of the SEBs and to discharge it in
future from general revenues. The State Government
(Energy Deptt.) vide their letter dated 25.11.2002
has confirmed that, they have in principle agreed to
implement Montek Singh Ahluwalia Committee’s
recommendations for settlement of outstanding dues
of CPSUs. Tripartite agreement for NTPC has already
been signed. For dues pertaining to other CPSUs,
the approval of Government has been sought and is
being processed.
1.12 Advantages to SEBs
The above recommendation would help the SEBs to
clean their balance sheets and place them in a
position where they can concentrate on solving the
current deficit problem, which itself is
formidable.
1.13 Since passing of the first Tariff
Order in September 02, the State Government and
MPSEB have entered into an Agreement with the Asian
Development Bank for bringing about restructuring
and reforms in the working of MPSEB. There was no
intimation to the MPERC either from the State
Government or the MPSEB about the conditions and the
terms included in the Agreement. It is necessary
that the MPSEB makes available the details of the
Agreement entered into with the Asian Development
Bank and the obligations and conditions which have
been imposed on the Board in lieu of the acceptance
of the loan. In their petition MPSEB have stated in
paragraph 2.1.5 “Incidentally, the MPSEB has
proceeded towards restructuring and reform
activities under the guidance and expertise of Asian
Development Bank (ADB). Success of reform programme
depends on the restructuring of electricity sector
and the development and implementation on sound
commercial principles. The elements of reform and
restructuring of the electricity sector include:-
· unbundling of generation, transmission and
distribution
· formation of separate independent
distribution companies (DISCOMS) of manageable size
· the introduction of private investment to
this sector”
1.14 In the petition, the MPSEB has
mentioned regarding their loan repayment liability
towards ADB loan, but have not informed the
Commission regarding the terms and conditionalities
imposed by the ADB. The Commission expects the
Board and the Government to provide the details of
these negotiations with the ADB to the Commission.
1.15 In their petition, the MPSEB has
stressed the need for timely revision of tariff and
has bemoaned the delays in doing so in the past. It
has cited the fact that before the setting up of the
Regulatory Commission, the Board could get a
revision in Tariff only at average intervals of 2½
years, i.e. in July, 1996, in March, 1999 and in
October, 2001. The Vidyut Sudhar Adhiniyam has given
the opportunity to the petitioner Board to request
for Tariff Revision once a year. We are now in the
third quarter of the Financial Year 2002-03 and by
this time the MPSEB should have got ready with their
proposal for 2003-04. If the Board fails in its
obligations to submit the petition in time, then it
has to bear the consequences for the same. The
delayed action by the MPSEB will no doubt have an
adverse impact on their financial health.
1.16 The Commission published the gist of
the Tariff Proposals received from the Petitioner
Board in the leading newspapers of Madhya Pradesh
inviting objections/suggestions/comments of the
interested persons and the State Government. The
public notices were published in the following
newspapers:
|
S.No.
|
Name of Newspaper
|
Edition
|
Date of Publication
|
|
1. |
Dainik Bhaskar (Hindi) |
All editions |
30.09.2002 |
|
2. |
Nai Duniya (Hindi) |
Indore edition |
01.10.2002 |
|
3. |
Nava Bharat (Hindi) |
Jabalpur edition |
01.10.2002 |
|
4. |
Hindustan Times (English) |
Bhopal edition |
30.09.2002 |
1.17 The Commission held public hearings
and meetings with the objectors on the petition
filed by MPSEB at the following places:-
|
Sr.No.
|
Place of Hearing
|
Date
|
|
1. |
Indore |
28th & 29th October,
2002 |
|
2. |
Gwalior |
31st October, 2002 |
|
3. |
Jabalpur |
7th November, 2002 |
|
4. |
Rewa |
8th November, 2002 |
|
5. |
Bhopal |
11th November, 2002 |
1.18 Before the commencement of public
hearings, a meeting of the State Advisory Committee
of the Electricity Regulatory Commission,
constituted under Section 33 of Vidyut Sudhar
Adhiniyam, was convened. This meeting was held at
Bhopal on 24th October, 2002.
1.19 After the first Tariff Order was
passed on 26.09.2001, the first Chairman of the
Electricity Regulatory Commission, Justice (Retd.)
Shacheendra Dwivedi has superannuated on 24th
January, 2002. His successor was appointed vide
M.P. Government Order dated 11.03.2002 and he joined
on 14th March, 2002. Member, Shri Rabindra Tripathy
also superannuated on 20th September, 2002 and since
then the Commission is working with only two Members
(including the Chairman).
In the subsequent chapters, the performance review
of MPSEB during the preceding few years and the
action taken by the Board on the directives given by
the Commission in the first tariff order have been
discussed in detail alongwith an analysis of the
proposals made by the petitioner and the objections
and comments received during the public hearing
meetings. |