|
MP
Power Transmission Co.Ltd., (MPPTCL) has submitted the first
compliance report of MPERC (Transmission Performance Standards)
Regulation 2004. The compliance report on the following performance
indicators is required to be submitted in the prescribed formats:
i. Voltage
Variation
ii.
Frequency
variation
iii.
Safety
standards
iv.
System
availability
v.
Feeder
availability
vi.
Transformer
availability
vii.
Voltage
unbalance
viii.
Neutral
voltage displacement
ix.
Voltage
variation index
x.
Frequency
variation index
xi.
Harmonics in
supply voltage
xii.
System
adequacy
xiii.
System
security
2. In compliance the MPPTCL
has submitted the report on only the following performance indicators:
i. Voltage
variation
ii.
Frequency
variation
iii.
Safety
standards
iv.
System
availability
v.
Feeder
availability
vi.
Substation
availability
3. The
detailed analysis on report of each of the performance parameters is
given below:
i. Voltage
Variation: MPPTCL has submitted the voltage
variation report for 400 kV and 200 kV substations only. The voltage
variation at 400 KV substation during the year 2004-05 was generally
within the prescribed limits of +5% and -10% except for Bina 400 kV
substation where in the quarters ending on Dec.04 and March 05 the
minimum voltage was in the range of -14%. For the 220 KV buses
situated in 400 kV substations and in 220 KV substations it is
observed that voltage variation in all 400 kV substations was within
the range i.e. in between +10% and -10%. For 220 kV substations, the
voltage variation was more during the quarter ending on Dec.04 & March
05. The minimum voltage limit violated frequently (in all the four
quarters) in the following substations:
|
Sl. No. |
Substation |
Minimum Voltage variation |
|
1 |
Burwaha 220 kV |
10.45% to -14.5% |
|
2 |
Dewas 220 kV |
13.18% to 22.73% |
|
3 |
Gwalior 220 kV |
13.64% to 29.09% |
|
4 |
Malanpur 220 kV |
16.36% to 29.09% |
|
5 |
Nepanagar 220 kV |
10% to -15% |
The highest order of voltage
variation recorded at Gwalior and Malanpur 220 KV substation i.e.
-29.09% or 156 KV. Nepanagar 220 KV substation has never witnessed the
voltage more than the rated voltage i.e. 220 KV during the year. It
remains below 220 KV for all the times.
The minimum voltages recorded
at 132 KV and 33 KV buses of the 220 KV substations also show that
the substations where the voltage limits have violated at 220 KV the
minimum voltage has also gone down considerably, i.e. -10% to -25%.
The voltage variation in the aforementioned substations at 132 kV and
33 kV was also more than -15%.
The Voltage profile of 132kV
and 66kV substations has not been submitted.
Direction: It is
directed that MPPTCL should identify the locations where frequently
low voltage has been observed and include those projects in the
Investment plan. MPPTCL should demonstrate the remedial measures with
cost benefit analysis. The voltage profile of 132kV and 66kV
substations shall be submitted as the distribution licensee is mostly
getting the power from these substations.
ii. Frequency
Variation: The frequency variation chart for all the four quarters
indicates that during the period from April 04 to Sept.04 for about
90% of time the frequency was in the range of 49.5 Hz to 50.5Hz and
from Oct.04 to March 05 the frequency was in the range of 49.0Hz to
50.0Hz. This indicates that the frequency was within the limits during
the year 2004.05.
iii.
With regard to
confirmation report on security standards, it is confirmed by MPPTCL
that the Indian Electricity rule 1956 have been complied with except
for very old few 132 kV transmission lines which are on double pole
structure and where ground wire shielding for the line is not
provided, but the protection against the lightning has been provided
at substations.
Direction: MPPTCL is
directed work out the cost benefit analysis if such transmission
lines on rail pole are converted into tower line.
iv.
The overall
system availability was above 98.8% during the year. The quarter wise
details are given below.
|
System Voltage |
Actual System Availability during
the Year 2004-05 |
|
April - June |
July - September |
October - December |
January - March |
|
400 kV |
99.93% |
98.62% |
99.97% |
98.88% |
|
220 kV |
99.87% |
98.25% |
99.83% |
98.71% |
|
132 kV |
99.83% |
99.57% |
99.83% |
99.26% |
|
Over All |
99.85% |
98.97% |
99.12% |
98.80% |
v.
With regard to the availability of lines,
for the quarters ending in June 2004 and September 2004 the
availability was about and above 95% except for 220 kV Katni - Damoh
DCDS line was available for 70% of time. In the quarter ending
December 2004 the availability of all the transmission lines was more
than 95% except 220 kV Ujjain-Modak line (availability 93%). During
the quarte ending March 2005, except for 132 KV Chhegaon Talwadia
Railway traction feeder (availability - 74%), for Bhopal Bairagarh
220 KV line (availability - 67%) and 400kV Itarsi Bhopal line
(Availability 92%), the availability for all the transmission lines
was 95% or more..
Direction: MPPTCL is
directed to pay special attention where the availability of lines is
less than 95% and analyze the cause. The reason for low availability
of Chhegaon Talwadia Railway traction feeder and Bhopal Bairagarh
220kV line should be analyzed and informed to the Commission..
vi.
With regard to
the transformer availability, except for the following transformer the
availability was generally more than 95%.
|
Substation |
Availability |
Quarter Ending on |
|
Mandideep 132 kV |
84% |
June 2004 |
|
Sarni 132 kV |
81% |
June 2004 |
|
Bhopal 400 kV |
85% |
September 2004 |
|
Malanpur 220 KV |
83% |
September 2004 |
|
Jamli 132 KV |
18% |
September 2004 |
|
Neemuch 220 KV |
76% |
December 2004 |
|
Substation |
Availability |
Quarter Ending on |
|
Indore 132 KV CH |
84% |
December 2004 |
|
Khandwa 132 KV |
84% |
December 2004 |
|
Nepanagar 220 KV |
42% |
March 2005 |
|
Mandla 132 KV |
84% |
March 2005 |
|
Shrinagar 132 KV |
90% |
March 2005 |
|
Indore 132 KV CH |
30% |
March 2005 |
Direction: MPPTCL is
directed to pay special attention where the availability of lines is
less than 95% and analyze the cause. The reason for low availability
of Indore 132 kV Chambal substation, Nepanagar 220kV substation, Jamli
132kV substation and Neemuch 220kV substation should be analyzed and
informed to the Commission.
Due to difficulty in collection of the data, the compliance report on
the following performance indicators have not been submitted by
MPPTCL. It is directed that the MPPTCL should immediately start
collecting the data and submit the detailed compliance report as
envisaged in the Transmission Performance Standards Regulation to the
Commission.
i. Voltage
Unbalance
ii.
Neutral
Voltage Displacement
iii. Voltage
Variation Index
iv.
Frequency
Variation Index
v.
Harmonics in
Supply Voltage
vi.
System
Adequacy and
vii.
System
Security
|