|
6.1
Regulatory Assets
The Petitioner has requested for creation of
regulatory asset as mentioned earlier in the Chapter
on Board’s Proposal. During the technical sessions
and subsequent discussions, the Commission had asked
the Petitioner to submit a time frame within which
it would be able to make a turnaround. As long as
the Petitioner is not able to make a turnaround,
creation of regulatory assets and its subsequent
recovery would further burden the consumers. Another
aspect, which deserves attention while addressing
the issue of creation of regulatory assets is the
level of accuracy in determining the losses incurred
by the Petitioner. Currently when there is no
certainty about the correctness of the losses as
projected by the Petitioner, a regular feedback to
the Commission about the same, an action plan to
reduce these losses and a diligent implementation of
the same, determination of regulatory assets would
be only a guesswork and an unnecessary burden on the
consumers. Hence, for the time being, creation of
regulatory assets is not being allowed. The
Petitioner should come up with a turnaround strategy
to demonstrate as to when it would be able to
achieve the break-even point in its cost of
operation and convince the Commission that the
operations of the utility are going to be efficient
and matching with the expectations of its consumers.
The petitioner must stake suitable steps in this
direction and only then present the details at the
time of filing the tariff petition for the year
2003-04. The request for regulatory asset will be
examined then, if full and detailed justification is
given for each item of unrealized revenue that is
proposed for inclusion in Regulatory Asset.
TOP
6.2
Demand and Load Forecast
6.2.1 The Commission, in the last tariff order
had observed that ‘in the absence of Board’s audited
accounts and necessary data in this regard, the
passing of tariff order is like shooting an arrow in
the dark’. The Commission feels that a similar
situation exists before the Commission in this year
too.
6.2.2 The Petitioner has generally adopted a 5
year Compound Annual Growth Rate (CAGR), consumer
category-wise, to project number of consumers,
connected load and energy sales for the year
2002-03. In certain categories, where the Petitioner
felt that the 5 year CAGR is not likely to be
achieved, it has modified the growth rate for
projecting data. Accordingly the Petitioner projects
to sell 15,062 million units of electricity to
different categories of consumers in the year
2002-03.
6.3
Agricultural Load Factor
6.3.1 The Commission had asked the Board to
conduct a survey for assessing pattern of energy
consumption and determination of load factor for
agriculture pumps. The MPSEB, in their proposal for
determination of tariff for the year 2002-2003
submitted details of energy consumption for 1275
pumps, together with additional details of 291 pumps
installed in Narmada Basin, for determination of
energy consumption and thereby has projected the
energy requirement for the year 2002-2003 for
agriculture pumps.
6.3.2 The pattern of survey for majority of
pumps is summarized below:
|
No. of Pumps |
Duration of consumption |
Period |
|
761 |
1 month |
November 2001 |
|
288 |
2 months |
November – December 2001 |
|
105 |
3 months |
November 2001 – January 2002 |
The above constitutes over 90% of the total pumps
covered in the sample study.
The pattern of survey in respect of majority of 291
pumps installed in Narmada Basin, where good water
potential is available through out the year is
summarized below:
|
No. of Pumps |
Duration of consumption |
Period |
|
52 |
1 month |
October 2001 |
|
110 |
2 months |
October - November 2001 |
|
65 |
3 months |
October – December 2001 |
|
54 |
4 months |
October 2001 – January 2002 |
The determination of per hp per month consumption
for the year 2002-2003 appearing at pages 235 to 250
and pages 47 to 49 of the Petition by the Board on
the basis of which the determination of load factor
for agriculture pumps has been done, is not the
representative figure because duration of
consumption is limited from 1 to 3 months only. The
details furnished regarding consumption in respect
of 137 pumps (metered pumps) for complete one year
has also not been considered any where for
determination of Tariff as mentioned over concluding
pages by MPSEB.
The consultants to the Commission studied the energy
consumption for 167 pumps spread over 7 regions of
MPSEB for a period of one year. Of these certain
pumps were not covered by MPSEB’s study which are
summarized below:
|
Division |
No. of pumps |
|
Sendhwa |
16 |
|
Burhanpur |
15 |
|
Jawra |
8 |
|
Mandsaur |
2 |
|
Datia |
1 |
The consumption of energy in respect of these 167
consumers under study with can be considered as
representative of agriculture consumption.
The check meters are normally installed at locations
of fair availability of water. The assessment of
consumption for agricultural pumps on the basis of
check meter reading is slightly on higher side. The
consideration of LF of 11.5% for agriculture pumps
for the year 2001-02 is thus fairly reasonable.
During field visits very less availability of water
potential was observed particularly in Ujjain and
Indore Regions. The consumption of power during
2002-2003 shall not therefore remain different to
what was observed during 2001-2002. During the
course of public hearings, consumers complained
about shortage of power available to agricultural
consumers. Taking these into consideration and
availability of power projected for 2002-03, the
Commission allows the agricultural consumption
projected at 4772.72 million units by the Board.
TOP
6.4 Other categories of Consumers
The availability of power has been discussed at
clause 4.7. Keeping in view availability of power
and T&D losses, discussed at clause 4.6, the Board
has 27854.46 million units available for sale, which
is more than the projected sale of energy. The
Commission has examined the increased availability
and the sale mix projected by the Board. If the
sourcing of energy is restricted to the sales
projected by the Board, it would result into
surrendering the allocated share of energy from
Central Sector Stations. This when seen in the light
of shortage of power in the State, does not appear
to be justified. The Board should procure energy to
the extent projected by them and undertake
additional sale in the State. For the purpose of
allocation of expected revenue from various
categories of consumers, the Commission has
proportionately increased the projected sale to
subsidized categories in the LT segment.
6.5 Aggregate sale projections for
2002-03
Accordingly the projected sale to different class of
consumers is summarized below:
Million units
|
S. no
|
Category
|
Projected sales for the year2002-03
|
Allowed by MPERC for tariff determination |
|
L T Consumers
|
|
1
|
Domestic
|
3256.76
|
3768.88
|
|
2
|
Single Light Point
|
132.28
|
132.28
|
|
3
|
Non-domestic
|
617.08
|
617.08
|
|
4
|
Water Works
|
167.58
|
193.93
|
|
5
|
Industrial
|
685.77
|
723.37
|
|
6
|
Agricultural
|
4772.72
|
4772.77
|
|
7
|
Street Lights
|
133.19
|
154.13
|
|
Total (LT)
|
8492.65
|
10362.43
|
|
H T Consumers
|
|
1
|
Railway Traction
|
1225.07
|
1225.07
|
|
2
|
Coal Mines
|
523.91
|
523.91
|
|
3
|
Mini Steel Plants
|
97.86
|
97.86
|
|
4
|
Cement Factories
|
553.50
|
553.50
|
|
5
|
HT Irrigation
|
10.55
|
10.55
|
|
6
|
HT Water Works
|
299.50
|
299.49
|
|
7
|
Other HT consumers
|
2385.58
|
2385.58
|
|
8
|
RE Co-operative Society
|
182.99
|
182.99
|
|
9
|
Border Villages
|
17.25
|
17.25
|
|
Total HT
|
5296.20
|
5296.19
|
|
Total LT + HT
|
13788.86
|
15658.62
|
TOP
6.6 T&D losses
6.6.1 The Board has indicated that during the
year 2002-03 it would be able to reduce T&D losses
by 5% from 48.77% during 2001-02. During the
discussions held with the State Govt. on 12 November
2002, Chairman, MPSEB mentioned that presently the
T&D losses of the Board are estimated to be 43%.
Secretary, MPSEB clarified that these losses are
excluding the losses in RE co-operative societies
network.
6.6.2 The T&D loss computed for the year 2001-02
based on 11.5% agricultural load factor comes out to
49.35% as against 48.77% mentioned by the Board in
the petition. The target for reduction of annual T&D
loss by the end of March 2003 is fixed at 42%.
However, for calculating Annual Revenue Requirement
for 2002-03, the average T&D loss has been taken as
43.77%. The Board shall report the actual T&D losses
to the Commission on monthly basis.
6.7 Total Energy Requirement
6.7.1 Thus on the basis of the sale to different
category of Consumers and T&D losses taken at
43.77%, the total energy required by the board for
2002-03 would be:
|
No.
|
Particulars
|
2000-01
|
2001-02
|
2002-03
|
|
Projected by MPSEB
|
MPERC
|
|
1
|
Net Generation (MUs)
|
12868.66
|
12852.42
|
14359.00
|
14650.00
|
|
2
|
Purchase of Energy (MUs)
|
13736.60
|
13746.61
|
13197.46
|
13197.46
|
|
3
|
Total Energy Available (MU)
|
26605.28
|
26599.05
|
27556.46
|
27842.46
|
|
4
|
T&D Loss (%)
|
50.97%
|
48.77%
|
43.77%
|
43.77%
|
|
5
|
T&D Loss (MUs)
|
13560.31
|
12972.22
|
12494.67
|
12188.83
|
|
|
6
|
Energy Sale (MUs)
|
13044.97
|
13626.83
|
15061.64
|
15658.63
|
|
|
|
|
|
|
|
|
TOP
6.8 Sourcing of Energy Requirement
6.8.1 Energy Generation
6.8.1.1 Thermal
In order to improve the performance during 2002-2003
and in the following years, the Board shall be
required to undertake serious efforts. It would need
to take remedial actions in respect of the
deficiencies noted earlier so as to cut down on the
partial loading of the units and reduction in their
forced outages resulting ultimately in the overall
improvement of various parameters. Accordingly, it
is directed that:
(i) The Board shall adhere to the scheduled
annual overhauling / maintenance programmes of the
various units and ensure its implementation. Capital
overhauling of the units shall also be carried out
periodically in accordance with the norms stipulated
by the manufacturers.
(ii) Board shall make all efforts in taking up
the refurbishment/ renovation / modernization work
of the various units so as to improve upon their
working life and performance.
(iii) Board shall make adequate funds available so
as to meet the regular maintenance needs of the
generating units.
(iv) In order to keep the operating parameters in
check and also to take care of due and proper
maintenance of various generating units and their
auxiliaries, it would be prudent to impart training
and refresher courses to the concerned employees
from time to time on the operation and maintenance
of various units.
(v) Board shall take up the matter with the
Government of India and Coal India Ltd. for supply
of adequate quantity of coal to its various thermal
power stations. Matters regarding quality of coal
wherever it is not upto the desired value shall also
be taken up with the Coal India for improvement.
Entering into Fuel Supply Agreement with coal
companies will be a right step in this direction.
(vi) Further, Energy Audit of the power stations is
bound to improve upon the performance parameters.
Therefore, a time bound programme shall be taken up
by the Board in this direction.
(vii) The Board should also evolve an appropriate
incentive scheme to motivate the employees for
achieving highest possible generation. Similarly
punitive measures may also be envisaged in the event
the actual performance is lower than the desired
minimum.
(viii) The Board is directed to file a report of
action taken on the above points every six months by
30th April and 30th October every year.
TOP
6.8.1.2 Plant Utilisation Factor (PUF)
The Commission has reworked the targets for
achieving PUF after taking into consideration the
following:
i) The annual maintenance
programme of the units. |
ii) Considering partial loss of
5%, and a loss in Generation to the tune of 10%
owing to forced outages of the unit.
iii) Considering the effect of rains
and wet coal during the rainy season of four months.
iv) Considering the generation at a
load factor of 75% of availability round the year,
as indicated by MPSEB in its petition.
v) Considering the age and physical
condition of the old units
vi) Taking into consideration that
in absence of renovation and modernization work for
2x120 MW units at Amarkantak TPS, these units
cannot generate beyond the unit capacity of 90 MW
each.
vii) That the generating units
especially the old ones do not have adequate spares
6.8.1.3
Amarkantak Thermal Power Station
Looking into all these circumstances and
limitations, Commission has fixed a generation
target of 202 MUs (46.12%) for Amarkantak power
house I and 1147 MUs (54.56%) for Amarkantak PH-
II. This makes a target of 1349 million units of
generation with PUF of 53.11 % for the whole
Amarkantak complex for the year 2002-2003.
TOP
6.8.1.4 Satpura Thermal Power Station
In addition to the scheduled overhauling of various
units at STPS, Unit no. 2 (62.5 MW of power station
no. 1) has been earmarked for capital overhaul
during 2002-03. Considering this and looking to the
circumstances and limitations explained earlier, the
proposal of MPSEB for generation of 75 Million Units
at a PUF of 74.9% for Satpura complex is
reasonable and is accepted.
6.8.1.5 Sanjay Gandhi Thermal Power Station
Brisinghpur
Unit no. 1 and 2 (2x120 MW) were commissioned during
the year 1993-94 and are 8-9 years old. Units 3 and
4 (2x210 mw) were commissioned during 1999 and are
only 2-3 years old. Taking into consideration this
fact and as explained above, the projection of MPSEB
for a generation of 5200 million units for the
complex with a PUF of 70.70% needs upward revision.
The Commission has therefore determined a generation
target of 2633 million unit (PUF of 71.67%) for
Phase I and a generation of 2700 MUs.(PUF of 73.4%)
for Phase II with overall generation of 5333 MUs.
with PUF of 72.47% for the complex as a whole for
the current year of 2002-2003.
Accordingly the aggregate thermal generation would
be 14,182 million units at an overall PUF of 71.25%
(M.P. Share: 13,382 million units). Power station
wise PUF proposed by the Board and now being fixed
by the Commission for the year 2002-2003 is
tabulated as given below:-
|
Sr. no.
|
Name of the power station
|
Capacity (MW)
|
Proposed by MPSEB
|
Fixed by Commission
|
|
MU
|
PUF (%)
|
MU
|
PUF(%)
|
|
1
|
Amarkantak I
|
1x30+1x20 = 50
|
200
|
45.7
|
202
|
46.12
|
|
2
|
Amarkantak II
|
2x120 = 240
|
1060
|
50.40
|
1147
|
54.56
|
|
3.
|
Amarkantak Complex
|
50+240= 290
|
1260
|
49.60
|
1349
|
53.11
|
|
4.
|
Satpura I
|
5x62.5 = 312.5
|
2000
|
73.1
|
2000
|
73.1
|
|
5.
|
Satpura II
|
1x200+ 1x210 =410
|
2700
|
75.2
|
2700
|
| |