                           Schedule of Miscellaneous Charges

The Electricity Regulatory Commission’s Act, 1998 (No. 14 of 1998) came into force w.e.f. 25th April, 1998, which provides for establishment of CERC and SERCs with the objectives of 

The Commission had earlier directed the MPSEB to come up with all types of miscellaneous charges for scrutiny of the Commission. This has not been complied with by the Board. However, a Schedule of existing Miscellaneous Charges has been submitted to the Commission by the Board on 27 November 2002. The MPSEB is hereby directed to come up to the Commission with detailed proposal for revision of miscellaneous and other charges, along with full justification by 31st December 2002, and till then the Commission allows the Board to levy the following miscellaneous charges:

 

Sl. No

Particulars of Charges

Unit

Charges/Rate

1

Changing of meter/meter/board

 

 

 

1. Changing or removing of meter board

Per job

Rs. 50/-

 

2. Changing of meter at the consumer's      request

Per job

Rs. 75/-

 

3. Resealing of cut out in consumer's premises if seal found broken

Per job

Rs. 55/-

 

4. Resealing of meter, MD indicator and instruments in Consumers’ premises if seal is found broken

Per job

 

 

(a) For single phase connections

 

 

 

   (i) L & F connection

Rs. 65/-

 

  (ii) Power connection. (Other than light and fan)

Rs. 112/-

 

(b) For Three phase LT connections

 

 

 

   (I) Industrial connection upto 10 BHP

Rs. 214/-

 

   (ii) Industrial connection above 10 BHP

Rs. 437/-

 

  (iii) Irrigation consumer upto 5 HP

Rs. 65/-

 

   (iv) Irrigation consumer for load above 5 HP

Rs. 108/-

 

(c) For All HT connection

Rs. 865/-

 

 

 

 

2

Replacement of fuses/glass/meter cards

 

 

1. Replacement of cut out fuses 

Per job

Rs. 20/- for one fuse or more than one fuse if all   replaced at the same time.

 

2. Replacement of consumer’s fuses (LT)

Rs. 20/- 

 

3. Replacement of missing meter cards

Per card

Rs. 10/- per card including clerical charges

 

4. Replacement of broken glass etc

Per glass

Rs. 24/-

 

 

 

 

3

Reconnection Charges

 

 

 

   (I) Upto 10 kW

 

 

 

       At cut out

Per job

Rs. 65/-

 

       At over head main

Rs. 150/-

 

       At undergound main

Rs. 400/-

 

   (ii) Over 10 kW upto 75 kW

Add 25% to (I) above.

 

   (iii) Over 75 kW (Special charges according to condition of load)

Add 50% to (i) above

 

 

 

 

4

Checking and Testing charges of various equipments on consumer's request

 

 

 

1. Contest fee for billing meters:

 

 

 

(a) Single phase energy meters

Per meter

Rs. 50/-

 

(b) Three phase meters w/o LT, CTs

Rs. 75/-

 

(c) Three phase meter with LT, CTs

Rs. 1000/-

 

(d) Special meter Bivector/Trivector

Rs. 1000/-

 

(e) Recording Type watt-hour Meters

Rs. 170/-

 

 (f) Maximum demand indicator/special meters

Rs. 335/-

 

 (g) Ammeters and Voltmeters

Rs. 65/-

 

 (h) Initial testing of meter at the time of installation

Nil

 

 (i) Subsequent testing and installation

Rs. 80/-

 

 

 

 

5

Charges for hire of metering system

 

 

 

 

 

 

 

Where it is property of Board

 

 

 

   (1) For 230/440 Voltages

 

 

 

        (a) Single phase meter

 

 

 

            (i) Without M.C.B.

Per meter/month

For Domestic, now 
embedded in the tariff and hence not to be levied separately

Rs. 12/-

 

              (ii) With M.C.B.

Per meter/month

Rs. 16/-

 

        (b) Poly Phase meter

 

 

              (i) Without M.C.B.   

Per meter/month

Rs. 25/-

 

              (ii) With M.C.B.

Per meter/month

Rs. 36/-

 

              (iii) LT Meter with CTs

Per meter/month

Rs. 45/-

 

              (iv) Demand or Speical type of meter

Per meter/month

Rs. 184/- or 2.3% per month per rupees of cost of metering system, whichever is higher

 

(2) For 11 kV Voltages

 

 

 

       (I) Electromagnetic meter

Per meter/month

Rs. 920/-

 

       (ii) Electro-static meter

Per meter/month

Rs.1540/-

 

(3) For 33 kV Voltages

 

 

 

       (I) Electromagnetic meter

Per meter/month

Rs. 1560/-

 

       (ii) Electro-static meter

Per meter/month

Rs. 2040/-

 

(4) For 132 kV Voltages

 

 

 

       (I) Electromagnetic meter

Per meter/month

Rs. 15630/-

 

       (ii) Electro-static meter

Per meter/month

Rs. 16120/-

 

(5) For 220 kV Voltage

 

 

 

       (I) Electromagnetic meter

Per meter/month

Rs. 32250/-

 

       (ii) Electro-static meter

Per meter/month

Rs. 32730/-

 

(6) For Special metering such as summation metering etc.

Per meter/month

2.3% of the cost of per metering and allied equipments

 

   (7) The HT consumers existing as on 30.6.2000

Per meter/month

2.3% per month per rupee of cost of metering system.