"Metro Plaza", 3rd & 4th Floor, E-5 Arera Colony, Bittan Market, Bhopal – 462  016

 
 

Tariff Schedule – LV - 10  

Temporary Supply 

 

 

 

Temporary Supply  

1           Applicability:

This tariff is for connections of temporary nature. The applicability shall be as given in respective category rate schedule.  

Temporary supply can not be demanded by a prospective consumer as a matter of right but will normally be arranged by the Board when a requisition giving due notice is made.

2                 Character of service:

Alternating Current, single/ three phase, 50 cycles, 230 volts or above depending upon the availability of the voltage of supply and at the sole discretion of MPSEB.

TOP 

3                 Point of Supply:

The power will be supplied to the consumers ordinarily at a single point for the entire premises.

4                 Tariff:

Category

Chargeable units

Tariff

LV 10.1   Domestic lights     and fans and power

 

For all units consumed

(a) Fixed Charge :
(i)    For single phase Rs. 90/-per month or part thereof.  
(ii)  For three phase Rs. 225/-per month or part thereof.

PLUS

(b) Energy Charges :  450 p/unit

LV 10.2  Non Domestic Light and Fans

For all units consumed

(a) Fixed Charge :  
(i)    For single phase Rs.150/-per month or part thereof.  
(ii)  For three phase Rs. 270/-per month or part thereof.

PLUS

 (b) Energy Charges :  525 ps/unit

LV  10.3 Water Works

For all units consumed

405 paise per unit subject to minimum charge Rs.120/- per month or part thereof per HP or part thereof of connected load.

LV10.4.1:Industrial      For connected load not  exceeding  25 HP

For all units consumed

600 paise per unit subject to  minimum charge of Rs. 270/- per month or part thereof per HP or part thereof of the connected load.

LV10.4.2:Industrial       For connected load above 25 HP but not exceeding 100 HP

For all units consumed

790 paise per unit subject to  minimum charge of Rs. 355/- per month or part thereof per HP or part thereof of the connected load.

LV 10.5  Agricultural Connections : (Only metered temporary supply shall be provided for agricultural connections)

For all units consumed

180 paise per unit subject to minimum charge of 30 units per month or part thereof per HP or part thereof the connected load.

Notes  
a)      Tariff under LV 10.5 i.e. temporary supply for agricultural consumption, the minimum period for charge would be two months provided the Junior Engineer concerned has satisfied himself that the transformer would not be overloaded beyond prescribed limit.  
b)      The fuel charge/ Variable cost  adjustment charge shall also be levied at 1.5 times the prevailing rate in addition for the respective category.  
c)      Connection and disconnection charges shall be paid separately.  
d)      Advance-Estimated energy consumption charges are payable in advance before serving the temporary connections subject to replenishment from time to time and adjustment as per final  bill after disconnection. 

TOP 

5                 Rounding off

All bills will be rounded off to the nearest rupee.

6                 Other Terms and Conditions

a)      This schedule is subject to the application of such corresponding provisions as may be applicable as per the relevant category Rate Schedule.

b)      No rebates/ concessions under any head would be applicable to connections under this category. 

c)      Late payment Surcharge: If the bills are not paid by the consumers within the period (due date) prescribed, a surcharge of 1.5% per month of the total amount of monthly bill (including outstanding arrears) will be payable in addition.

d)      Fuel/ Variable Cost Adjustment (VCA) Charge: Fuel charge/ VCA charge, if any, shall be levied  in addition to energy charge.

e)      Meter Hire – Meter Hire shall be charged as per the Schedule of Miscellaneous Charges. Part of a month will be reckoned as full month for purpose of billing.

f)        The billing demand shall be the demand requisitioned by the consumer or the highest monthly maximum demand during the period of supply commencing from the  month of connection ending with the billing month, whichever is higher

g)      The month for the purpose of temporary supply shall mean 30 days from date of connection or for further part thereof.

h)      Any expenditure  up to point of supply  shall be paid by the consumer as per prescribed procedure.

i)        Connection and Disconnection Charges shall be paid separately

j)        In case of any dispute on applicability of tariff on a particular LT category , the decision of the Commission shall be final and binding.

k)      The tariff  does not include any tax or duty, etc. on electrical energy that may be payable at any time in accordance with any law then in force. Such charges, if any, shall be payable by the consumer in addition to the tariff charges.  

l)        Notwithstanding the provisions, if any, contrary to the agreement entered into by the consumer with the Board, all conditions prescribed herein shall be applicable to the consumer.

 PREVIOUS |TOP | NEXT