Information on Tripping/Breakdown/Outage of Generating Units of MPPGCL |
|||||||
| S.No | Name of Generating Station | Unit No | Time & Date when unit trip/shutdown for Maintenance | Time & date of unit comes on Bar | Total duration of Outage of unit | Reason of Outage | Name & Designation of Message Sender |
| 1 | Gandhi Sagar Hydel Power Station | Unit No.3 | 11.00Hrs/ 16.01.2006 | 16.45 Hrs/ 16.01.2006 | 5.45 Hrs | Inspection/Maintenance of 132 KV SF-6 Breaker mechanism by M/s BHEL Expert | A.K. Tailor, S.E. (O&M), MPPGCL, Gandhisagar HPS vide fax dt.17.01.06 |
| 2 | Unit No 1. | 10.25 Hrs / 17.01.2006 | 11.50 Hrs / 17.01.2006 | 1.25 Hrs | |||
| 3 | Unit No 3. | 13.40 Hrs / 17.01.2005 | 15.10 Hrs. / 17.01.2006 | 1.30 Hrs | |||
| 4 | Unit No. 4 | 20.25 Hrs/ 19.01.06 | 17.25 Hrs/ 20.01.06 | 21.00 Hrs | Bulcholze and R&B phase differential relay operated | fax dt.20.01.06 | |
| 5 | Pench Hydel Power Station | 80 MW Unit No.2 | 11.13 Hrs./ 11.01.06 | 17.47 Hrs 15.02.2006 | 840.30 Hrs | Unit de-synchronized due to Generator Bottom guide bearing temp. high | D.K. Mishra, SE (O&M) PENCH vide fax dt. 17.02.06 |
| 6 | Gandhi Sagar Hydel Power Station | Unit No.2 | 06.15 Hrs./ 23.01.06 | 11.30 Hrs./ 23.01.06 | 05.15 Hrs. | 132 KV Breaker mechanism problem | A.K. Tailor, S.E. (O&M), vide fax dt.23.01.06 |
| 7 | Unit No.3 | 12.30 Hrs./ 23.01.06 | 17.50 Hrs. / 23.01.06 | 5.40 Hrs. | 132 KV SF-6 Breaker problem | ||
| 8 | SGTPS, Birsinghpur | Unit No.4 | 09.25 Hrs./ 24.01.06 | 2.15 Hrs 26.01.06 | 40 Hrs 50 Min. | Primary Super heater leakage | S.E. (OPN-I), SGTPS, vide fax dt.24.01.06 |
| 9 | Gandhi Sagar Hydel Power Station | Unit No. 1 | 5.50 Hrs / 27.01.06 | 10.05 Hrs / 27.01.06 | 04.15 Hrs. | 132 kV SF-6 Breaker mechanism maintenance work | A.K. Tailor, S.E. (O&M), MPPGCL, Gandhi Sagar HPS |
| 10 | Gandhi Sagar Hydel Power Station | Unit No. 3 | 11.40 Hrs./ 27.01.06 | 16.50 Hrs / 27.01.06 | 05.10 Hrs | 132 kV SF-6 Breaker mechanism maintenance work | A.K. Tailor, S.E. (O&M), MPPGCL, Gandhi Sagar HPS |
| 11 | Gandhi Sagar Hydel Power Station | Unit No. 3 | 10.20 Hrs./ 29.01.2006 | 14.35 Hrs./ 29.01.2006 | 04.15 Hrs. | 132 kV SF-6 Breaker mechanism maintenance work | B.R. Pancholi, SE (O&M), MPPGCL, Gandhisagar HPS |
| 12 | Unit No. 1 | 10.00 Hrs./ 30.01.2006 | 10.45 Hrs./ 29.01.2006 | 00.45 Hrs | 132 kV SF-6 Breaker mechanism maintenance work | ||
| 13 | ATPS Chachai | Unit No. II | 23.00 Hrs./ 01.02.2006 | 07.50 Hrs./ 04.02.06 | 56.50 Hrs | Tube leakage of Boiler No. 3 | S.E. (O&M), PH-I ATPS, CHACHAI |
| 14 | STPS Sarni | Unit No.2 | 10.47 Hrs./ 06.02.06 | Feed control valve problem and air heater tube chocking | D.K. Dubey, S.E. | ||
| 15 | SGTPS, Birsinghpur | Unit No.2 | 11.35 Hrs./ 07.02.2006 | 13.02 Hrs./ 07.02.2006 | 1.34 Hrs | Tripped on Drum level very low | S.E. (OPN-I), SGTPS, vide fax dt.07/02/06 |
| 16 | SGTPS, Birsinghpur | Unit No.4 | 09.57 Hrs 15.02.2006 | 07.00 Hrs. 17.02.06 | 45.03 Hrs | Boiler tube leakage | S.E. (OPN-II), SGTPS, vide fax dt.15/02/06 |
| 17 | SGTPS, Birsinghpur | Unit No.1 | 12.18 Hrs./ 16.02.2006 | 19.47 Hrs 20.02.2006 | 103.29 Hrs | To attend tube leakage | S.E. (OPN-I), SGTPS, vide fax dt.16/02/06 |
| 18 | Gandhi Sagar Hydel Power Station | Unit No. 3 | 19.43 Hrs./ 16.02.06 | 15.20 Hrs. / 17.02.06 | 20.17 Hrs | Unit tripped on stator earth fault. | B.R. Pancholi, S.E. (O&M), MPPGCL, Gandhi Sagar HPS |
| 19 | ATPS Chachai | Unit No. I | 23.22 Hrs./ 22.01.2006 | Boiler No.3. Tube Leakage | S.E. (O&M), PH-I ATPS, CHACHAI | ||
| 20 | ATPS Chachai | Unit No. II | 10.55 Hrs./ 19.02.2006 | 02.30 Hrs. 22.02.06 | 51.35 Hrs | For attending M.S. Line drain valve of T.G. Set | S.E. (O&M), PH-I ATPS, CHACHAI fax dt. 23.02.06 |
| 21 | Gandhi Sagar Hydel Power Station | Unit No. 3 | 09.45 Hrs./ 11.02.06 | 14.40 Hrs. / 11.02.06 | 02.00 Hrs. | Main cooling water valve attending work | A.K.S. Rathore, E.E. (EMD), MPPGCL, Gandhi Sagar HPS vide letter No 344 dt 11.02.06 |
| 22 | SGTPS, Birsinghpur | Unit No.2 | 16.25 Hrs./ 21.02.2006 | 17.57 Hrs./ 21.02.2006 | 1.32 Hrs | Condenser Pressure very high | S.E. (OPN-I), SGTPS, vide fax dt.22/02/06 |
| 23 | ATPS Chachai | Unit No. II | 12.33 Hrs./ 23.02.2006 | 22.05 Hrs./ 05.03.2006 | 249.32 Hrs | Tube leakage of Boiler No. 1 | S.E. (O&M), PH-I ATPS, CHACHAI fax dt. 24.02.06 |
| 24 | SGTPS, Birsinghpur | Unit No.2 | 22.05 Hrs./ 23.02.2006 | 21.12 Hrs./ 25.02.06 | 71.30 Hrs | To attend tube leakage | S.E. (OPN-I), SGTPS, vide fax dt.24/02/06 |
| 25 | SGTPS, Birsinghpur | Unit No.1 | 14.28 Hrs./ 27.02.2006 | 16.10 Hrs./ 27.02.06 | 1.42 Hrs | Low lub. oil pr. after filter | S.E. (OPN-I), SGTPS, vide fax dt.27/02/06 |
| 26 | Gandhi Sagar Hydel Power Station | Unit No. 2 | 18.12 Hrs./ 26.02.06 | 19.25 Hrs. / 26.02.06 | 01.13 Hrs. | 132 Kv MOCB mechanism checking work | B.R. Pancholi, S.E. (O&M), MPPGCL, Gandhi Sagar HPS vide letter No 476 dt 27.02.06 |
| 27 | ATPS Chachai | Unit No. I | 09.05 Hrs./ 01.03.2006 | 09.47 Hrs./ 01.03.2006 | 42 Minutes | Avr Problem | S.E. (O&M), PH-I ATPS, CHACHAI fax dt. 01.03.06 |
| 28 | STPS Sarni | Unit No.6 | 13.58 Hrs./ 03.03.06 | Feed control valve problem and air heater tube chocking | Shri R.K. Datey S.E. OPN PHI | ||
| 29 | Gandhi Sagar Hydel Power Station | Unit No. 3 | 10.15 Hrs./ 03.03.06 | 11.15 Hrs./ 03.03.2006 | 1.00 HRS | 11 KV XLPE cable termination kit indoor (1 NO. in R Phase) replacement work | S.E. (O&M) MPPGCL, Gandhi Sagar HPS vide letter No 548 dt 03.03.06 |
| 30 | STPS Sarni | Unit No.7 | 09.05 Hrs./ 11.03.06 | Generation Stator Earth fault | S.E. OPN PHII | ||
| 31 | STPS Sarni | Unit No.7 | 17.15 Hrs./ 20.03.06 | Tube leakage in boiler | Shri S.K. Shah S.E. OPN PHII | ||
| 32 | SGTPS, Birsinghpur | Unit No.4 | 11.00 Hrs./ 22.03.2006 | 12.44 Hrs./ 22.03.06 | 44 Min. | Tripped on furnace pressure very high falling of cinker suspected. | S.E. (OPN-II), SGTPS, vide fax dt.23/03/06 |
| 33 | SGTPS, Birsinghpur | Unit No.3 | 13.25 Hrs./ 22.03.2006 | Hand tripped at 13.25 hrs due to suspected tube leakage in primary super heater | S.E. (OPN-II), SGTPS, vide fax dt.23/03/06 | ||
| 34 | ATPS Chachai | Unit No. I | 10.30 Hrs./ 13.03.2006 | 15.20 Hrs./ 14.03.2006 | 25.50 Hrs | Turbine Governing System problem | S.E. (O&M), PH-I ATPS, CHACHAI letter dt. 16.03.06 |
| 35 | STPS Sarni | Unit No.6 | 15.20 Hrs./ 27.03.06 | 15.35 Hrs 27.03.06 | 15 Min. (Information gathered on Phone) | Hand trip due to closing of both ESV | Shri S.K. Shah S.E. OPN PHII vide SMS dt27.03.06 |
| 36 | ATPS Chachai | Unit No. II | 08.55 Hrs./ 23.03.2006 | 13.45 Hrs./ 24.03.2006 | 28.50 Hrs | Boiler feed pump 2B problem | S.E. (O&M), PH-I ATPS, CHACHAI letter dt. 28.03.06 |
| 37 | ATPS Chachai | Unit No. I | 13.57 Hrs./ 24.03.2006 | 15.07 Hrs./ 25.03.2006 | 25.10 Hrs | Failure of Unit Auxiliaries electrical supply | S.E. (O&M), PH-I ATPS, CHACHAI letter dt. 28.03.06 |
| 38 | ATPS Chachai | Unit No. II | 14.15 Hrs./ 25.03.2006 | 00.30 Hrs./ 26.03.2006 | 10.15 Hrs. | Boiler feed pump 2B lub. oil problem | S.E. (O&M), PH-I ATPS, CHACHAI letter dt. 28.03.06 |
| 39 | SGTPS, Birsinghpur | Unit No.3 | 18.20 Hrs./ 25.03.2006 | 01.45 Hrs 26.03.06 | 7.25 Hrs | Instrument Air supply failure | S.E. (OPN-II) SGTPS, MPPGCL, Birsinghpur |
| 40 | ATPS Chachai | Unit No. I | 23.45 Hrs./ 02.04.2006 | 00.45 Hrs 05.04.06 | 49.00 Hrs | Steam Governing system problem of TG Set No.1 | S.E. (O&M), PH-I ATPS, CHACHAI letter dt. 3.04.06 |
| 41 | STPS Sarni | Unit No.6 | 17.10 Hrs./ 01.04.06 | 18.50 Hrs. 03.04.06 | 49.40 Hrs | Fur Press very high due to water wall tube leakage. | Shri S.K. Shah S.E. OPN PHII vide SMS dt02.04.06 |
| 42 | Gandhi Sagar Hydel Power Station | Unit No. 5 | 10.30 Hrs./ 16.03.06 | 11.30 Hrs./ 05.04.2006 | 481 Hrs | Guide vane and packing sleeve line leakage attending work. Generator routine maintenance work | Shri A.K. Tailor, DY. P.S.S. MPPGCL, Gandhi Sagar HPS vide letter dt 18.03.06 |
| 43 | ATPS Chachai | Unit No. I | 10.00 Hrs./ 07.04.2006 | 18.35 Hrs./ 07.04.06 | 08.35 Hrs | Steam Governing system problem of TG Set No.1 | |
| 44 | ATPS Chachai | Unit No. I | 21.45 Hrs./ 12.04.2006 | 03.12 Hrs. 16.04.06 | 77.27 Hrs. | Steam Governing system problem of TG Set No.1 | S.E. (O&M), PH-I ATPS, CHACHAI |
| 45 | ATPS Chachai | Unit No. I | 17.20 Hrs./ 16.04.2006 | 19.40 Hrs./ 18.04.2006 | 48.20 Hrs | Steam Governing system problem of TG Set No.1 | S.E. (O&M), PH-I ATPS, CHACHAI |
| 46 | SGTPS, Birsinghpur | Unit No.1 | 18.20 Hrs./ 25.03.2006 | 01.45 Hrs 26.03.06 | 7.25 Hrs | Instrument Air supply failure | S.E. (OPN-II) SGTPS, MPPGCL, Birsinghpur |
| 47 | ATPS Chachai | Unit No. I | 10.45 Hrs./ 20.04.2006 | 19.15 Hrs./ 21.04.06 | 32.30 Hrs. | Steam Governing system problem of TG Set No.1 | S.E. (O&M), PH-I ATPS, CHACHAI |
| 48 | ATPS Chachai | Unit No. I | 09.10 Hrs./ 09.04.2006 | 05.035 Hrs./ 12.04.06 | 68.25 Hrs | Steam Governing system problem of TG Set No.1 | S.E. (O&M), PH-I ATPS, CHACHAI |
| 49 | Gandhi Sagar Hydel Power Station | Unit No. 3 | 10.15 Hrs./ 27.04.06 | 17.50 Hrs./ 27.04.2006 | 07.35 HRS | For Governor and valve checking work | S.E. (O&M) MPPGCL, Gandhi Sagar HPS vide letter No 952 dt 28.04.06 |
| 50 | STPS Sarni | Unit No.7 | 21.20 Hrs./ 01.05.06 | 17.15 Hrs./ 03.05.06 | 44.55 Hrs. | Trip on generation overall difference in Y and B phase | Shri S.K. Shah S.E. OPN PHII |
| 51 | ATPS Chachai | Unit No. I | 09.17 Hrs./ 30.04.2006 | 08.25 Hrs./ 01.05.06 | 23.08 Hrs | Steam Governing system problem of TG Set No.1 | S.E. (O&M), PH-I ATPS, CHACHAI |
| 52 | STPS Sarni | Unit No.3 | 09.24 Hrs./ 02.05.06 | Due to tripping of generator bkr trip | Shri R.K. Datey S.E. OPN PHI | ||
| 53 | STPS Sarni | Unit No.2 | 20.45 Hrs./ 29.04.06 | 00.40 Hrs 01.05.06 | 28.25 Hrs | Due to tube leakage in Primary super heater zone | Shri R.K. Datey S.E. OPN PHI |
| 54 | STPS Sarni | Unit No.3 | 11.02 Hrs./ 06.05.06 | 12.22 Hrs./ 06.05.06 | 01.20 Hrs | Due to tripping of generator bkr trip | Shri R.K. Datey S.E. OPN PHI |
| 55 | ATPS Chachai | Unit No. I | 18.50 Hrs./ 02.05.2006 | 16.40 Hrs./ 03.05.06 | 19.50 Hrs | Failure of 132/33 KV electrical supply due to tripping of old auto transformer. | S.E. (O&M), PH-I ATPS, CHACHAI |
| 56 | ATPS Chachai | Unit No. II | 18.50 Hrs./ 02.05.2006 | 21.35 Hrs./ 02.05.06 | 2.45 Hrs | Failure of 132/33 KV electrical supply due to tripping of old auto transformer. | S.E. (O&M), PH-I ATPS, CHACHAI |
| 57 | STPS Sarni | Unit No.4 | 00.38 Hrs./ 12.05.06 | 15.15 Hrs./ 13.05.06 | 38.37 ?Hrs | Due to tube leakage in final super heater | Shri R.K. Datey S.E. OPN PHI |
| 58 | STPS Sarni | Unit No.2 | 19.30 Hrs./ 11.05.06 | 13.07 Hrs./ 17.05.06 | 137.37 Hrs. | Due to tube leakage in primary super heater | Shri R.K. Datey S.E. OPN PHI |
| 59 | STPS Sarni | Unit No.6 | 22.00 Hrs./ 09.05.06 | 15.00 Hr./ 11/05/06 | 42.00 Hrs | Due to Re-heater tube leakage | Shri S.K. Shah S.E. OPN PHI |
| 60 | STPS Sarni | Unit No.1 | 23.21 Hrs./ 12.05.06 | 06.50 Hrs./ 14.05.06 | 31.29 Hrs | Due to tube leakage in Super heater | Shri R.K. Datey S.E. OPN PHI |
| 61 | STPS Sarni | Unit No.5 | 03.05 Hrs./ 16.05.06 | 03.40 Hrs,/ 16.05.06 | 00.35 Hrs | Due to bus fault at Itarsi | Shri R.K. Datey S.E. OPN PHI |
| 62 | STPS Sarni | Unit No.1 | 18.27 Hrs./ 16.05.06 | 06.27 Hrs./ 17.05.06 | 12.00 Hrs | Due to tube leakage in water wall. | Shri R.K. Datey S.E. OPN PHI |
| 63 | SGTPS, Birsinghpur | Unit No.4 | 10.15 Hrs./ 23.05.2006 | 13.40 Hrs 23.05.06 | 03.25 Hrs | Unit tripped on low vacuum | S.E. (OPN-II) SGTPS, MPPGCL, Birsinghpur |
| 64 | STPS Sarni | Unit No.6 | 06.25 Hrs./ 27.05.06 | 01Hr.15 Min 26.06.06 | 29 days & 18.50 min | Due to Water wall tube leakage | Shri S.K. Shah S.E. OPN PHI |
| 65 | STPS Sarni | Unit No.1 | 22.58 Hrs./ 25.05.06 | 17.30 Hrs./ 26.05.06 | 18.32 | Due to tube leakage in economizer zone | Shri R.K. Datey S.E. OPN PHI |
| 66 | SGTPS, Birsinghpur | Unit No.1 | 15.00 Hrs./ 26.05.2006 | 01.00 Hrs 29.05.06 | 58.00 Hrs | Suspected Tube leakage in boiler | S.E. (OPN-II) SGTPS, MPPGCL, Birsinghpur |
| 67 | SGTPS, Birsinghpur | Unit No.2 | 20.52 Hrs./ 26.05.2006 | 23.02 Hrs 26.05.06 | 02.10 Hrs | Furnace pressure low | S.E. (OPN-II) SGTPS, MPPGCL, Birsinghpur |
| 68 | ATPS Chachai | Unit No. II | 04.45 Hrs./ 26.05.2006 | 10.45 Hrs./ 26.05.05 | 06.00 Hrs. | Main steam temperature became low due to failure of main feed water control station of boiler No.2 | S.E. (O&M), PH-I ATPS, CHACHAI |
| 69 | ATPS Chachai | Unit No. I | 04.45 Hrs./ 26.05.2006 | 00.53 hrs./ 06.06.06 | 260.08 hrs | Main steam temperature became low due to failure of main feed water control station of boiler No.2 | S.E. (O&M), PH-I ATPS, CHACHAI |
| 70 | STPS Sarni | Unit No.3 | 16.49 Hrs./ 31.05.06 | 13.18./Hrs 01.06.06 | 20.29./Hrs | Due to tube leakage in economize | Shri R.K. Datey S.E. OPN PHI |
| 71 | SGTPS, Birsinghpur | Unit No.3 | 17.40 Hrs./ 31.05.2006 | 17.20./ Hrs 02.06.06 | 47.40 Hrs | Tube leakage | S.E. (OPN-II) SGTPS, MPPGCL, Birsinghpur |
| 72 | STPS Sarni | Unit No.7 | 7.35 am./ 02.06.06 | 8.20 a.m./ 02.06.06 | 45 minutes | Due to gen over voltage | Shri S.K. Shah S.E. OPN PHI |
| 73 | SGTPS, Birsinghpur | Unit No.2 | 23.00 Hrs./ 04.06.2006 | 00.24 hrs 07.06.06 | 49.24 hrs | Boiler Tube leakage | S.E. (OPN-II) SGTPS, MPPGCL, Birsinghpur |
| 74 | STPS Sarni | Unit No.3 | 14.38 Hrs./ 02.06.06 | 17.38 hrs./ 03.06.06 | 27.00 hrs | Due to tube leakage in economize | Shri R.K. Datey S.E. OPN PHI |
| 75 | STPS Sarni | Unit No.5 | 12.10 Hrs./ 03.06.06 | 12.27 Hrs./ 03.06.06 | 00.17 hr | Due to tst operated on low vacuum | Shri R.K. Datey S.E. OPN PHI |
| 76 | STPS Sarni | Unit No.1 | 22.25 Hrs./ 06.06.06 | 07.10 Hrs./ 07.06.06 | 08.45 hrs | Due to condenser tube leakage | Shri R.K. Datey S.E. OPN PHI |
| 77 | STPS Sarni | Unit No.5 | 15.07 Hrs./ 05.06.06 | 14.45 Hrs | Shri R.K. Datey S.E. OPN PHI | ||
| 78 | STPS Sarni | Unit No.1 | 21.25 hrs 08.06.06 | 0.17 HRS 09.06.06 | 12.42 Hrs | Due to heavy leakage in feed line | Shri K.N. SINGH, E.E. OPN PHI |
| 79 | STPS Sarni | Unit No.2 | 0.37 hrs 10.06.06 | 00.52 hrs,/ 11.06.06 | 24.15 hrs | Due to Clinker formation | Shri K.N. SINGH, E.E. OPN PHI |
| 80 | STPS Sarni | Unit No.7 | 2.45 hr./ 11.06.06 | 11.25 hrs./ 14.06.06 | 70.40 hrs | Due to both IDFANOFF | Shri S.K. Shah S.E. OPN PHI |
| 81 | STPS Sarni | Unit No.1 | 03.52 hrs 11.06.06 | 17.44 hrs./ 12.06.06 | 37.52 hrs | Due to Boiler tube leakage | Shri K.N. SINGH, E.E. OPN PHI |
| 82 | SGTPS, Birsinghpur | Unit No.2 | 01.10 Hrs./ 07.06.2006 | 02.41 hrs./ 07.06.06 | 01.31 hrs | Drum lvl v/hi protection | S.E. (OPN-I) SGTPS, MPPGCL, Birsinghpur |
| 83 | STPS Sarni | Unit No.5 | 13.13 hrs./ 15.06.06 | 9.52 hrs,/16.06.06 | 30.39 hrs | Due to Boiler tube leakage | Shri K.N. Singh E.E. H.Q. PHI Sarni |
| 84 | STPS Sarni | Unit No.4 | 13.22 hrs./ 19.06.06 | 14.50 hr 16.07.06 | 27 days | Due to abnormal sound and vibration in turbine (APOH) | Shri K.N. Singh E.E. H.Q. PHI Sarni |
| 85 | SGTPS, Birsinghpur | Unit No.2 | 06.45 Hrs./ 23.06.2006 | 07.39 hrs./ 23.06.06 | 00.54 hrs | Drum lvl v/hi protection | S.E. (OPN-II) SGTPS, MPPGCL, Birsinghpur |
| 86 | STPS Sarni | Unit No.6 | 07.15 Hrs./ 26.06.06 | 16.32 hrs./ 28/06/06 | 58.20 hrs | Due to tube leakage due to flowrestriction in water wall | Shri S.K. Shah S.E. OPN PHI |
| 87 | ATPS Chachai | Unit No. II | 11.07 Hrs./ 26.06.2006 | 07.30 hrs./ 27.06.06 | 20.23 hrs | Boiler No.2 & 4 under forced shutdown due to non availability of PF mills & tube leakage respectively. | S.E. (O&M), PH-I ATPS, CHACHAI |
| 88 | STPS Sarni | Unit No.6 | 23.55 Hrs./ 28.06.06 | 22.55 HRS./ 30.06.06 | 47.00 HRS | Due to Water wall tube leakage | Shri S.K. Shah S.E. OPN PHI |
| 89 | STPS Sarni | Unit No.3 | 0.25 Hrs./ 01.07.06 | 11.24 Hrs./ 03.07.06 | 59.00 Hrs | Due to tube leakage | Shri K.N.Singh E.E. HQ |
| 90 | STPS Sarni | Unit No.6 | 02.Hr.15 Min./ 03.07.06 | 18.15 Hrs./ 07.07.06 | 112 Hrs | Due to suspected tube leakage | Shri S.K. Shah S.E. OPN PHI |
| 91 | SGTPS, Birsinghpur | Unit No.2 | 22.52 Hrs./ 02.07.2006 | 00.57 hrs./ 03.07.06 | 02.05 hrs | Furnace Pressure V/Lo | S.E. (OPN-I) SGTPS, MPPGCL, Birsinghpur |
| 92 | SGTPS, Birsinghpur | Unit No.3 | 09.58 Hrs./ 05.07.2006 | 11.26 Hrs./ 05.07.06 | 01.26 Hrs | Unit tripped on drum level very high | S.E. (OPN-I) SGTPS, MPPGCL, Birsinghpur |
| 93 | SGTPS, Birsinghpur | Unit No.3 | 21.30 Hrs./ 05.07.2006 | 22.50 Hrs./ 05.07.06 | 01.20 Hrs | Furnace Pressure V/Lo | S.E. (OPN-I) SGTPS, MPPGCL, Birsinghpur |
| 94 | ATPS Chachai | Unit No. II | 08.38 Hrs./ 30.06.06 | 13.20 hrs./ 02.07.06 | 52.42 hrs | S.E. (O&M), PH-I ATPS, CHACHAI | |
| 95 | STPS Sarni | Unit No.1 | 12.35 Hr../ 05.07.06 | 12.45 Hr.,/ 06.07.06 | 24.10 Hrs | Due to condenser hardness | Shri K.N.Singh E.E. HQ |
| 96 | Gandhi Sagar Hydel Power Station | Unit No. 2 | 18.35 Hrs./ 07.07.06 | 23.40 Hrs./ 07.07.2006 | 05.05 HRS | For 132 KV Breaker mechanism checking work | S.E. (GEN) MPPGCL, Gandhi Sagar HPS |
| 97 | STPS Sarni | Unit No.5 | 11.14 Hr../ 10.07.06 | 14.14 Hr.,/ 10.07.06 | 02.44 Hrs | due to falls tripping | Shri K.N.Singh E.E. HQ |
| 98 | SGTPS, Birsinghpur | Unit No.2 | 11.20 Hrs./ 12.07.2006 | 19.45 Hrs./ 14.07.06 | 56.25 Hrs | Boiler tube leakage | S.E. (OPN-I) SGTPS, MPPGCL, Birsinghpur |
| 99 | STPS Sarni | Unit No.9 | 11.50 Hr../ 12.07.06 | 13.05 Hr.,/ 12.07.06 | 01.15 Hrs | Due to turbine hand tripped due to low drum level | Shri R.K. Datey S.E. OPN PHI |
| 100 | SGTPS, Birsinghpur | Unit No.1 | 15.30 Hrs./ 13.07.2006 | 17.35 hrs./ 13.07.06 | 02.05 hrs | Boiler Furnace Pressure Very High | S.E. (OPN-I) SGTPS, MPPGCL, Birsinghpur |
| 101 | |||||||
| 102 | STPS Sarni | Unit No.6 | 19.00 Hr../ 15.07.06 | 09.07 Hr.,/ 17.07.06 | 38.07 Hrs | Due to water wall tube leakage | Shri S.K. Shah S.E. OPN PHI |
| 103 | STPS Sarni | Unit No.4 | 22.58 Hr../ 16.07.06 | 07.06 Hrs./ 17.07.06 | 08.06 Hrs | Due to BFP.4B Outage. | Shri K.N.Singh E.E. HQ |
| 104 | ATPS Chachai | Unit No. II | 05.20 Hrs./ 15.07.06 | Due to Boiler No. 1 & 2 under forced shutdown due to tube leakage. | S.E. (O&M), PH-I ATPS, CHACHAI | ||
| 105 | SGTPS, Birsinghpur | Unit No.2 | 02.55 Hrs./ 17.07.2006 | 18.20 Hrs./ 21.07.06 | 111.25 Hrs. | Boiler tube leakage | S.E. (OPN-II) SGTPS, MPPGCL, Birsinghpur |
| 106 | STPS Sarni | Unit No.5 | 06.35 Hr../ 18.07.06 | 07.30 Hr.,/ 18.07.06 | 00.55 Hrs | Shri H.K. Acharya S.E (OPN)PH-1 | |
| 107 | STPS Sarni | Unit No.2 | |||||