APDRP PROGRESS UP TO 31.12.05
UJJAIN REGION TOWNS (Ratlam, Dewas, Mandsaur, Neemuch, Shajapur, Shujalpur)
SL.NO Particulars of work Unit INDORE REGION
Provision  Achievement
Physical Fin.(Lac) Physical Fin.(Lac)
1 33/11 KV Substation          
a New Nos 10 492.9    
b Capacity Addition Nos 3 49.54    
2 33KV lines          
a New lines Kms 124.6 481.4    
b Reconductoring Kms 20.5 41.2    
c Add Bay at EHV S/S Nos 5 85    
d Add Bay at 33/11 KV S/S Nos        
3 Installation of new VCB/circuit  Breakers          
a 33 KV Nos        
b 11KV Nos        
4 Replacement of defective OCB/VCB          
a 33KV  Nos 15 45    
b 11KV Nos 45 75.45    
  Recurement of Isolators D/Box, LA Nos 1506 15.75    
a DO At 33/11 KV S/S Nos        
b AB Switch          
  33 KV Nos 4 0.3    
  11 KV Nos 810 40.5    
4 11 KV Lines          
a New lines Kms. 214 646.8    
b Reconductoring Kms. 107 152    
c Add Bay 11KV Nos 1 1.5    
d 11KV DP Nos        
5 11/0. 4KV Distn. Transformer Nos 694 310.9    
6 Renovation of Distn. Transfomer Nos 1240 187.4    
7 Conversation of LT line to HT (11 KV)          
a i ON ACSR/AAAC Cond Kms.   50    
b ii ON ABC Cable Kms.        
8 Armoured cable          
9 L.T Line          
a a New Line Kms. 141 365.54    
b b Recondutoring and renovation Kms. 272 431.5    
10 Revamping of S/S and Data Longing Nos. 18 95    
11 Building at S/S Nos. 18 50    
12 Computarised Billing Nos. 23 206.5    
13 Improvement of Service Conn. Nos.        
14 Renovation of Consumer services Nos.        
15 DT Metering Nos. 1157 228.63    
16 Other Works LS 39 877.35    
  TOTAL     4930.16   0.00
Other expenditure Viz in Mobalisation  Advance & departmental Purchase 50.00
 Total 50.00