APDRP PROGRESS OF SHIVPURI
Sl.No Item Unit PROVISION PROGRESS(AS ON 30.11.05)
Works DPR COST    (Rs in lakhs) Works Amount Remarks
1 DT Metering Nos 198 49.5      
2 Consumer indexing Nos 23435 11.72      
3 Sub station R&M Nos 2 32      
4 DT R&M Nos 198 19.8      
5 Billing center Nos 1 2 1 2  
6 Computerised billing Nos 1 12   0.8  
  Computers  printers A/C etc Nos          
7 MIS/ Call center etc Nos 2 7      
8 New 33KV line Km 16 55.08 1.2 14.15 1.5Km. U/p
9 Reconductoring of 33KV Km 5 4.2      
10 New 11KV line Km 32.5 100.86 0.4 0.41  
11 Reconductoring of 11KV feeders Km 3.45 3.95      
12 Bifurcation Km 1.5 6.3      
13 AB Cable Km 20 63      
14 New LT line Km 3 7.5      
15 LT line Reconductoring Km 32 31.98 14 13.25 18.35Kms U/p
16 New sub station Nos 1 50 1 50 U/p S/s Charged
17 DTs in new feeders Nos 58 116 2 2 U/p
  Total     572.89   82.61