| APDRP PROGRESS OF SHIVPURI | |||||||
| Sl.No | Item | Unit | PROVISION | PROGRESS(AS ON 30.11.05) | |||
| Works | DPR COST (Rs in lakhs) | Works | Amount | Remarks | |||
| 1 | DT Metering | Nos | 198 | 49.5 | |||
| 2 | Consumer indexing | Nos | 23435 | 11.72 | |||
| 3 | Sub station R&M | Nos | 2 | 32 | |||
| 4 | DT R&M | Nos | 198 | 19.8 | |||
| 5 | Billing center | Nos | 1 | 2 | 1 | 2 | |
| 6 | Computerised billing | Nos | 1 | 12 | 0.8 | ||
| Computers printers A/C etc | Nos | ||||||
| 7 | MIS/ Call center etc | Nos | 2 | 7 | |||
| 8 | New 33KV line | Km | 16 | 55.08 | 1.2 | 14.15 | 1.5Km. U/p |
| 9 | Reconductoring of 33KV | Km | 5 | 4.2 | |||
| 10 | New 11KV line | Km | 32.5 | 100.86 | 0.4 | 0.41 | |
| 11 | Reconductoring of 11KV feeders | Km | 3.45 | 3.95 | |||
| 12 | Bifurcation | Km | 1.5 | 6.3 | |||
| 13 | AB Cable | Km | 20 | 63 | |||
| 14 | New LT line | Km | 3 | 7.5 | |||
| 15 | LT line Reconductoring | Km | 32 | 31.98 | 14 | 13.25 | 18.35Kms U/p |
| 16 | New sub station | Nos | 1 | 50 | 1 | 50 | U/p S/s Charged |
| 17 | DTs in new feeders | Nos | 58 | 116 | 2 | 2 | U/p |
| Total | 572.89 | 82.61 | |||||