APDRP PROGRESS OF GUNA
Sl.No Item Unit PROVISION PROGRESS (AS ON 30.11.05)
Works DPR COST (Rs in lakhs) Works Amount Remarks  
1 System metering (feeder & DT) Nos 15 1.56 15 1.56 Departmental 14
2 Computerised billing computers printers  Nos LS 5 2 1.06 Departmental 13
3 Consumer indexing Nos 22570 11.28 0 0 Departmental  
4 MIS/Call center etc Nos 1 2 0 0 Departmental  
5  Service connection Nos 10210 30.63 3404 14.5 Departmental 12
6 Re-conductoring of 33KV feeders Kms 7.2 8.75 5 8.75 Departmental 9
7 New sub station Nos 1 48.13 U/p 48.05 Departmental 1
8 New 33KV line Kms 10 24.1 8.75 20.5 Departmental 4
9 DT R&M Nos 126 12.6 100 10 Turn key 11
10 Sub station R&M Nos 3 3.75 1 1.3 Turn key 2
11 Re-conductoring of 11KV feeders Kms 10 12 3.7 4.96 Turn key 8
12 New 11KV lines Kms 30 45 U/p 60.82 Turn key 5
13 New LT Lines Kms 3.1 5.23 0 0 Turn key  
14 DTs in new feeders Nos 25 30 25 87 Turn key 3
15 LT Lines re-conductoring Kms 40 44 0.75 2.08 Turn key 10
16 LT Line bifurcation Kms 25.33 40.53 1.7 3.57 Turn key 6&7
17 LT Line cabling Kms 21 56.28 0 0 Turn key  
        380.84   264.15    
379.28
380.84
1.56