APDRP PROGRESS OF MANDIDEEP
Sl.No Item Unit PROVISION   PROGRESS           (AS ON 30.11.05)
 
Physical Financial   Physical Financial
 
A Priority works            
1 Consumer Meters1PH            
2 Consumer Meter 3phase            
3 FeederMeters Nos 4 4   6  
  DTMeters Nos 40 2.6      
5 Consnumer  indexing            
6 Substation R&M Nos 2 30 5    
  33KV VCB Nos 16 48 1 5 16.51
  11KV VCB Nos 9 18   1 7.79
7 DT R&M  Nos 194 47.75   25 4.05
8 Billing centers Nos 2 6      
9 Computerization & IT for MIS Nos 1 5      
10 Call centers Nos 2 3      
  Computerization data logging   1 24      
11 Strengthening works            
a 33KV Lines in Km            
b 11KV Lines in Km            
c LT Lines in Km            
12 33KV Lines             
a New Kms 5.5 27.73     13.53
b Reconductoring Kms 7 11      
13 11KV Lines             
a New Kms 4 8.15     3.85
b Reconductoring Kms 22.41 22.41   11.19 4.66
14 LT Lines            
a New Kms 18.5 27.55      
b Reconductoring Kms 15 18      
15 Sub-station             
  New Nos 1 50.38   U/P 32.4
  Power Trsfs(Additional) Nos 2 28   1 11.8
  Augumentation Nos 1 7.09   1 7.09
  33KV VCB Nos 2 6      
  11KV VCB Nos 6 12      
16 DTs Nos 31 42.45   7 10.1
17 1200KVAR Capacitor bank with bay & equipments Nos 3 15   2 10
18 Renovation of service lines  Kms 207 35.17   19 7.83
20 Conversion of LT to HT Nos 14 54   6 2.96
21 Fire fitting provision  Nos 2 0.70      
  ABC cable Kms 3 3      
  LT less cable Kms 30 22.52   45.07 36.94
  Special type pannel meters  Nos 190     322 14.86
        579.5     184.37