APDRP PROVISION AND PROGRESS OF BHOPAL CITY  2005-06
Sl.No Particulars Unit PROVISION PROGRESS (AS ON 30.1.05)
Physical Financial (Rs. in lacs) Physical Financial (Rs. in lacs) Remark
1 Consumers            
  a) Single phase(Electronic) Nos 180831 0      
  b) Three phase(Electronic) Nos 32418 0      
2 Feeder Meter with CTPT units Nos 159 79.5 159 79.5  
3 DT Meters Nos 2653 961.2 264 62.22  
4 Consumer Indexing Nos 214365 107 214365 107  
5 DTS   734 1446 283 425.42  
  a) 200KVA Nos 0        
  b) 100KVA Nos          
  c) 63KVA Nos          
  L.T. Less KM 272 443.36 217.2 401.39  
7 Computerisation of IT for M/S LS   356.25 116PC's 120  
8 Call centers Nos 7 14 23 66.56  
9 33KV Lines            
  a) New KM 17 59.5 13.61 125.68  
  b) Reconductoring  KM 42.2 65.41      
10 11KV Lines            
  a) New KM 20 35 29.28 97.27  
  b) Reconductoring  KM 53 65.19 9.5 11.69  
11 L.T. Lines            
  a) New KM 28 47.32 1.9 3.4  
  b) Reconductoring  KM 164 285.36 1.1 0.3  
12 Power Transformer (Additional) Nos 5 104.4 4 143.31 Chandbad , Karod & Ram Mandir
13 Addl. Bay with 33KV VCB Nos 3 12 1 7.35  
14 Addl. Bay with 11KV VCB Nos 12 39.6 6 13.26  
15 Renovation of service lines KM 3328 819.89 1318.3 380.71  
16 Conversion of LT to HT  Nos 96 168 43 41.15  
17 Conversion of single to three phase Nos 56 30.8 0 0  
18 Ladder Jeep Nos 7 42 0 0  
19 Walkie & Talkie Nos 30 4.5 0 0  
20 Fire fighting provision LS   5 0 0  
21 ABC Cable KM 9 28.35 0.25 0.79  
22 S/S R&M Nos 33 82.5 0 2.02  
23 DT R&M Nos 2653 172.5 498 65.14  
24 Billing Centers Nos 14 70 14 66.18  
25 Sub-station Nos 7 316.6 5 233.6 Mandi,E-8, Cancer Hospital, Kamala Nehru & Chambal
26 VCBs            
  a) 33 KV Nos 23 73.83 0 0  
  b) 11 KV Nos 26 43.42 0 0  
27 11KV Capacitor Bank Nos 8 37.6 8 46.74  
        6016.08   2500.68