APDRP PROVISION AND PROGRESS OF GWALIOR (O&M) 2005-06
Sl.No Particulars Unit PROVISION PROGRESS  (AS ON 30.11.05)
Physical Financial (Rs. in lacs) Physical Financial (Rs. in lacs) Remark
1 New 33/11KV Sub Station Nos 10 582.22 8 363.8 4No. W/C, 4Nos U/P(Including cost of 33KV & 11KV Line) 
           
             
2 Augumentation of power X'mer Nos 12 118.38 12 100.15  
3 Sub-station equipments            
  a) 33KV VCB Nos 10 253.55 10 188.46 U/P
  b) 11KV VCB Nos 82   71    
4 Installation of New Distribution X'mer   953 1702.03 71 105.25  
5 Shifting of Distribution Nos 94 9.4      
6 Renovation of Distribution Nos 3164 189 1360 138.52 On turn Key
7 Building work at Sub- Nos 31 62 23 37.94 15No. W/C.8Nos U/P
8 Computer Billing Nos 3 75      
9 Sub-station Computer + fitting + Cabling   31 93      
10 33KV Lines            
  a) For new sub-station KM 114 0 55   37 Kms U/p
  b)For bifurcation of 33KV feeder KM 63 123 0.7 6.31  
  c) Reconductoring of 33KV feeder KM 79 108.23 79 100.96  
11 11KV Lines            
  a) New KM 56.4 0 11.4   21.5 Kms U/p
  b)For shifting of DTs KM 47 73.79      
  c)For new DTs KM 460 728.8      
  d)Bifurcation of 11KV feeder KM 51 75.73      
  e) Reconductoring of 11KV feeder KM 397.58 286.12 358.7 247.15  
  f) Installation of ABC Cable KM 6.5 20.47      
12 Convertion of LT to 11KV line (For LT less system) KM 138.1 24.85      
13 LT Lines            
  a) Reconductoring  KM 444 377.36 223 128.26  
  b)Remodling of LT Line along highways KM 47 29.87      
  c) Armoured Cable KM 71 62.1 38.34 18.16 Progress obtained Deptt
14 Improvement of service connection Nos 20000 60 1471 8.71  
15 LT Capacitors at DTs Nos   60      
16 Energy Meter (Single Ph.) Nos 632 4.48 632 4.48  
17 DT Meters Nos 108 14.26      
Total 5133.64   1448.15